Weekly Update – I-10 Tune Up Pavement Rehab


Work continues for the I-10 Tune Up, Pavement Rehabilitation project. Please note, this schedule is subject to change. For the latest, visit the I-10 Tune Up page at https://i10tuneup.com/.

RIVERSIDE, CA – The California Department of Transportation (Caltrans) is continuing construction on Interstate 10 (I-10) from Beaumont to State Route 111 (SR-111). The following information is for the week of September 12 to 17, weather dependent:

During daytime work hours of 6 a.m. to 6 p.m. Monday through Friday, construction crews will continue electrical work and perform roadway excavation, joint seal improvements and shoulder pavement operations going both directions from 8th St in Banning to SR-111.

Alternating lane and ramp closures will occur during nighttime work hours, from 7 p.m. to 6:30 a.m., Sunday through Thursday:Demolition, paving, joint seal operations and grinding going both directions for entire project length.Install k-rail and construction signs from Beaumont Ave to Hargrave going eastbound.Remove existing k-rail going westbound from 8th St to Main St.
Crews have been moving into the next crossover in Segment 1, which will occur going eastbound from east of Beaumont Ave in Beaumont to Hargrave in Banning. The current crossover (from 8th St to Main St) is being removed, and lanes will open as normal, with some width restrictions. This new crossover is anticipated to be in place by mid-September. Motorists should anticipate a new traffic shift in the area to accommodate the crossover.

Due to the fuel spill incident that occurred on Wednesday, September 1, the eastbound Hargrave onramp will be closed until further notice. The eastbound 8th St and Ramsey St onramps may also be closed on an as needed basis.

The following are anticipated 10-day ramp closures. During these 10-day closures, the ramps will be improved. Closures will begin during nighttime work hours and reopen at the end of the night shift:WB Morongo Trail offramp is anticipated to close September 7 and reopen September 18. Commuters should use Main St or Malki as a detour WB Ramsey offramp is anticipated to close September 13 and reopen September 24. Commuters should use 8th St as a detour. WB Malki offramp is anticipated to close September 19 and reopen September 30. Commuters shoulder use Morongo Trail or Main St as a detour. WB Morongo Trail onramp is anticipated to close September 19 and reopen September 30. Commuters should use Main St or Malki as a detour. WB Fields Rd offramp is anticipated to close September 19 and reopen September 30.
This schedule is subject to change and is weather dependent. Know before you go! To stay on top of roadwork in the Inland Empire go to Caltrans District 8 and sign up for commuter alerts. Follow us for the latest information on Facebook and Twitter. To assist in planning your commute, view live traffic conditions using QuickMap and planned lane closures.

For those with sensory disabilities requiring alternate formats (i.e. Braille, large print, sign language interpreter, etc.) and those needing information in a language other than English, please contact Public Affairs at 909-383-4631 or TTY 711.